Larch Street Library: Slate and copper

Larch Street Library

A 1913 Carnegie library: the hipped slate roof relaid, and the cornice and box gutters re-lined in 20 oz copper.

Roof
5,200 sq ft
On site
12 weeks
Cornice
Copper, soldered by hand

The brief

The library’s box gutters, built into the cornice, had been patched with tar for decades. Water was running behind the stone and staining the reading room ceiling.

What we found

The slate was good. The box gutters were not: the original tin linings had been tarred over four or five times, and the wood under them had rotted along two sides.

What we did

  1. Opened the cornice and replaced rotten gutter boards with new fir, shaped to the original profile.
  2. Re-lined the box gutters in 20 oz copper with soldered flat-lock seams and expansion joints every 30 feet.
  3. Relaid the lower three courses of slate over the new gutter edge, and repointed the hips.
  4. Kept the library open throughout, working from scaffold towers with a covered entrance.

How it ended

Two winters since, the reading room ceiling is dry. The copper has gone bronze and will turn green along the cornice over the next twenty years.

“They found the problem nobody else had looked for, and fixed that instead of selling us a roof.”

Facilities manager, library district
Copper gutter linings formed on site
Copper gutter linings formed on site
Hip slate after the first rain
Hip slate after the first rain

How the time went

One foreman for the whole job, and a written update at the end of every week.

Weeks 1–3
Scaffold, open the cornice
Weeks 4–9
Gutter boards and copper linings
Weeks 10–12
Slate courses, hips, scaffold down

Let’s get on your roof.

Forty-five minutes on the ladder, photos of every plane and a written price within 48 hours. Free inside Portland city limits.

Leaking now? Leak line (503) 555-0149